On Now
Coming Up
  • Thu., Dec. 18, 2014 5:00 PM - 11:59 PM CST Lambeau Field Atrium closed

    The Lambeau Field Atrium and all businesses will be closing at 5 p.m. on Thursday, December 18 for a private function. Last "seating" at Curly's Pub will be at 3 p.m.

  • Fri., Dec. 19, 2014 12:15 PM - 12:30 PM CST Live McCarthy press conf. Packers Head Coach Mike McCarthy will be available to the media on Friday, Dec. 19, in the Lambeau Field media auditorium.
  • Sat., Dec. 20, 2014 6:30 PM - 7:30 PM CST Packers Everywhere pep rally

    Packers fans 21 years and older are invited to bring the spirit of Green Bay to the Tampa Bay area a day early with two free Packers Everywhere Pep Rallies on Saturday, Dec. 20.

    The festivities will take place at two different locations in the Tampa Bay area Saturday. The main pep rally will be held from 6:30 to 7:30 p.m. EST at Ferg’s Sports Bar & Grill, located at 1320 Central Ave., St. Petersburg, Fla. The second event will be held from 8:15 to 9 p.m. at The Varsity Club, located at 24091 US Hwy 19 N., Clearwater, Fla.

  • Sat., Dec. 20, 2014 8:15 PM - 9:00 PM CST Packers Everywhere pep rally

    Packers fans 21 years and older are invited to bring the spirit of Green Bay to the Tampa Bay area a day early with two free Packers Everywhere Pep Rallies on Saturday, Dec. 20.

    The festivities will take place at two different locations in the Tampa Bay area Saturday. The main pep rally will be held from 6:30 to 7:30 p.m. EST at Ferg’s Sports Bar & Grill, located at 1320 Central Ave., St. Petersburg, Fla. The second event will be held from 8:15 to 9 p.m. at The Varsity Club, located at 24091 US Hwy 19 N., Clearwater, Fla.

  • Sun., Dec. 21, 2014 12:00 PM - 3:00 PM CST Packers at Tampa Bay Buccaneers Packers at Tampa Bay Buccaneers
  • Mon., Dec. 22, 2014 6:00 PM - 7:00 PM CST Lacy, Clinton-Dix appearance Packers Eddie Lacy and Ha Ha Clinton-Dix are scheduled to appear at the Big Red Kettle at Bay Park Square Mall on behalf of the Salvation Army bell-ringing campaign.

News

Print
RSS

Lambeau Field Atrium renovations set to begin this offseason

Posted Jan 8, 2013

Work is final phase of stadium renovation project that began in 2011


The Green Bay Packers will begin renovations to the Lambeau Field Atrium this offseason and will continue work on the project through the next two offseasons, with work scheduled to be fully complete in June of 2015.

Highlights of the project include a new Packers Pro Shop, located in what will be a revamped lower level of the Atrium, new locations for the Packers Hall of Fame and Curly’s Pub, a new east-side entry gate to enhance ingress and egress, and a larger Oneida Nation Gate that includes a plaza area and a more prominent connection to Oneida Street.

Additionally, the players’ parking lot will move to the south side of the Oneida Nation Gate, with access via a tunnel under the enlarged gate. This enhancement will further open up access to the east side of the Atrium, with parking adjacent to the new east side entrance.

“We’re excited to begin work this offseason on the Atrium renovation,” said Packers President/CEO Mark Murphy. “We’re looking forward to providing all our guests an even better experience. The design and new layout will benefit everyone.”

The project, with a cost of $140.5 million, is the final phase of stadium renovation work that began in 2011 and included a new sound system, new video boards, two new gates and approximately 7,000 new seats in the south end zone. Funding for this phase will come from the Packers through private financing ($85.5 million) and a loan from the NFL G4 program ($55 million). In total, including the current project in the south end zone, renovations to the stadium will cost $286.5 million, with no funding coming from public tax money.

During the course of the renovation, the Packers Pro Shop will remain open as it transitions from its current to its new location. The Packers Hall of Fame and Curly’s Pub will close while their new locations are being constructed. The date and duration of closing periods will be determined when more detailed construction plans are established.

In addition to the public areas, the football facilities will receive some upgrades as well, including space for conditioning and team walkthroughs. This aspect of the renovations keeps the team’s football operations up-to-date with the latest technology and best practices.

This phase of the renovation will continue to be an economic impact and benefit to the community. The second phase is expected to employ approximately 1,500 workers over the next two years and provide more than $60 million in wages.

 